Model | [ ] AON M2+ (CE) | [ ] AON M2+ (R-NZ) | [ ] AON M2+ | [•] AON-M2 2020 | [ ] AON-M2 |
Category | [•] Preventive | [ ] Corrective | |||
Frequency | [ ] Daily | [•] Weekly | [ ] Monthly | [ ] Yearly | [ ] As Needed |
The procedure that follows gives instructions on how to inspect the six build chamber halogen light bulbs.
Estimated time: 15 minutes
None required.
None required.
Qty | Description | Minimum Specification |
---|---|---|
1 | Safety Eyewear | ANSI/ISEA Z87.1 |
Make sure that there are no prints on the build surface. Remove print(s) before the procedure that follows is started. Failure to do so can cause a collision and cause damage to the machine component(s).
Wait until all machine components are at room temperature before you continue. Some machine components can be hot if the machine was recently used. Failure to do so can cause injuries.